COG Blog: Weekly Updates on Construction

Thank you, Alice Dunn and Valerie Perkins, for your tireless work and your weekly updates! Click on any photos to enlarge. Also, you can check out photo galleries from Joe Turner here.
June 13 Update from your Construction Oversight Group (COG)


Be sure to check out the sky view of our new building with its many roof lines. See Joe Turner’s latest drone photos from this afternoon!

Lots happening over the last week:  More HVAC equipment has been installed. The first phase of interior wallboard is complete. Preliminary electrical and plumbing inspection are completed.  And, now 3 full days of insulation are underway. Exterior site work continues with foundation waterproofing (thanks to a few consecutive dry days!), and installation of many trench drain pipes. The first Alaskan Cedar siding boards have arrived and are being prepared. They are so beautiful and smell so good!

Alice & Valerie


June 6 Update from you Construction Oversight Group (COG)

We were so glad to welcome many Follenites to another site walkthrough after service last week!

We on COG are always so happy to get a chance to talk about the project, and all the various measures we are taking to plan for resiliency, accessibility, and delight!

This week we enjoyed the sight of vast quantities of wallboard being delivered.

We are expecting lots more site work in the next two weeks, too.

-Alice and Valerie


Check out this recent article from the Colonial Times!


May 30 Update from you Construction Oversight Group (COG)

Site walkthrough this Sunday (June 2) after service! If you didn’t get a chance to walk though the building project last time, or are curious to see what’s happening, come join us on guided tours of the project!

Here’s the plan: right after service lets out, we will be starting tours from the former French For Kids entry door (off the Waldorf driveway). One COG/CCC guide will take a 10 person group at a time, giving a little space between each group, on a roughly 10-minute tour. The site is a construction zone, so no sandals please, but hard hats won’t be required.

Where we are now:  town inspections of rough plumbing and wiring are complete and the wall-boarders have started on the interior walls! HVAC ducting is largely in place and the chiller arrives in the next week or so. The elevator is being assembled, and you’ll see it in the CC.

Rev. Claire joined us as we walked through confirming switching and outlets and all sorts of other details.
The Sonin Room is going to be so great!


As to the project timeline: You’ll note that the windows aren’t in yet, and boy oh boy, are we eager to see them go in. But they won’t be here for a few more weeks, and the siding is a bit delayed, so the realistic move-in is end of July, not June, as we had hoped.  But we are still making lots of good progress and are very happy with what is developing.


May 23 Update from your Construction Oversight Group (COG)

The Ikea assembly party was a huge success! Thanks to Valerie and Stephen’s extraordinary organization skills, 14 Fearless Follenites assembled a giant pile of cabinet boxes and drawers, ready to be installed in our new Kitchenettes, copier room, and meeting room. Thanks to all who came – and very thankful for the sunny day – with just the right level of skills!
The birth of a drawer
The garage workshop


Back at the site, as promised, insulation of the roof is done and fireproofed. The Sonin Room sound has already improved enormously and we’ve been happily imagining all the new activity to come. We’re also very glad to see the new insulation/waterproofing of the undercroft stone foundation walls. B&G has wanted this for decades.  The spray foam insulation is painted with a thin layer of fire-retarding intumescent paint (google that!).


And, many many sub-contractors are installing many many feet of conduit, wiring, ducting, AV low-voltage wiring. We expect rough-in inspections for electrical and plumbing in the next day or so, and then next week, the drywallers will take over. Everything will completely change! In the meantime, we enjoyed the impromptu cup-holder (last photo). Onwards, ever onwards!  Alice and Valerie (who’s off on a well-deserved vacation)

May 16 Update from your Construction Oversight Group (COG)

IKEA assembly folks: you know who you are!  Thanks in advance to the 12 or so Follenites who have already volunteered to help build cabinets. This Saturday, May 18, at the Perkins/Ervin home, we will be assembling cabinets, and folks are still welcome to join. The schedule remains: work from 9am – 3pm (allowing for the 3-5 pm tea for Lucinda), in several teams of 2-3. Come all day, or just for a few hours. Please contact Alice or Valerie (construction@follen.org) to let us know if you are coming!

On site, to keep ahead of the fast-moving HVAC installers, the roof insulation is underway: The insulation starts with a coat of closed cell spray foam up in the rafter bays and then they add a thicker layer of open cell spray foam below. They stopped the operation so we could do our walk-through inspection; by now, the whole roof is insulated. (See photo as Mart Ojamaa casts his eagle eye!) Many thanks to Mart and Nancy Sofen, who carefully and laboriously cleaned out and re-graveled the drainage in our Undercroft, prior to insulation of those original rubble-stone walls!

Once the roof insulation is complete, the attic HVAC ducting will installed. Rough wiring and plumbing inspections are expected next week and then wallboarding will start; we’re told that there may be a crew of 20 plasterers on site at once. They will make fast work of this project!

Looking forward to a sunny and warmer weekend, Alice and Valerie


May 9 Update from your Construction Oversight Group (COG)

Calling all IKEA assembly folks! On Sat. May 18, at the Perkins/Ervin home, we’ll be assembling cabinets. (See photo of shipment in the the garage!) We’ll be working from 9am – 3pm (allowing for the 3-5 pm tea for Lucinda), in several teams of 2-3. Come all day, or just for a few hours. Bring a screw gun and lots of good humor, and please contact Alice or Valerie to let us know if you are coming!

On site, now that the building is mostly weathertight, the interior is full of subcontractors, working away on framing details, installing electrical wiring, HVAC ducting, the roof hatch for access to our new hood vent, etc.   The new CC entry roof is underway, complete with cool steel posts that are configured for the wood cladding.

And Nancy and Mart and Alice are ‘breaking in’ our incoming President, Rosemary Trowbridge, so she’ll be up and running for July 1. We’re standing on the North Terrace, where new meets old. The Sanctuary window is blocked to protect it from all the commotion, but once the exterior is done, it’ll be back open!

And ever onward, Alice and Valerie


May 2 Update from your Construction Oversight Group (COG)

What a wonderful Sunday after church: we were able to conduct the promised – and long hoped-for – walkthrough of the new construction! We on COG were just thrilled to finally be able to share our vision with so many of you. We think about 90-100 Follenites, young and old, toured through the freshly-framed spaces. It was such a pleasure to take you all up to the new top floor, to see the Music Room and all the new meeting rooms/classrooms and the new stairs.

The only part that wasn’t completely framed was the North Stair, and here’s a few familiar faces enjoying all of our first walk on the new flights. For those of you who didn’t get to join us, we will have more opportunities.

In the meantime, we have been working intensively to get details of the HVAC (Heating, Ventilation, and Air Conditioning) system sorted out, coordinate our new fire sprinkler system, and get the undercroft and all the exterior walls and roofs ready for insulation. We’re still working on our Landscape plans, selecting finishes and working to reduce costs. And we’ve had our first planning session with the J2 team (Jane and Jackie) about moving back in!

And we’ll see you at Annual Meeting!

Onward, Alice and Valerie


April 25 Update from your Construction Oversight Group (COG)

Site Walk-through is still possible this Sunday.

Well, good news and less good news: the good news is that plants are happy with all the rain, and as of this writing, we are really, really close to having a fully closed-in building.

But the less good news is that the rain has delayed our building framers just enough so that we are still tentative on our planned walk-through for this Sunday right after service.  We’ll let you all know at service on Sunday- crossed fingers! The big issue is safety and waterproofing- with the predicted rain on Saturday, we need to be confident that we can safely allow groups to go through. But never fear, we can always try for another Sunday in May.

If we go ahead, here’s the plan: right after service lets out, we will be starting tours from the former French For Kids entry door (off the Waldorf driveway). One COG/CCC guide will take a 10 person group at a time, giving a little space between each group. The 10- minute tour will end over at the new Terrace area between Sanctuary and Marshman. The site is a construction zone, so no sandals please, but hard hats won’t be required.

In the meantime, here’s a few photos from this sunny day, as the site is drying out (until the next rainstorm!).


The roof of the elevator and north stair was just completed. The steps are part of the new North stairway, the section up from Sanctuary level to Offices level, next to the elevator shaft. Our architect, Maryann Thompson, is gazing up at where the next flight of stairs will go. We continue to be very happy with the new spaces that are being created, and look forward to sharing the full experience of both the new stairways and all the new circulation patterns!

Soggily and sunnily yours, Alice and Valerie


April 18 Update from your Construction Oversight Group (COG)

Save the date (tentative)! On Sunday April 28, after church, please plan for a walk-through of the new spaces (weather and progress dependent, of course). We believe the framing will be far enough along to invite all you patient Follenites to take a managed tour up into the new floor levels, to see what we have all created. Hard hats will not be required, as no one will be doing construction on Sunday, but it is an active site. Children are welcome, with a parent or responsible adult, and they must be carefully supervised the whole time. And we’ll be watching out for adults, too!  Choir members who are going to a 1 pm event get the first tours.

Here’s a few teaser photos –  The top of the South stair (on the Waldorf driveway side), and Claire in the Sonin Room (Which will have a roof in the next few days!)


And here’s us and our design team, hard at work on the HVAC coordination, as the rough-in of plumbing, electrical, and heating/cooling systems is well underway.


We’ll provide more details next week!
Alice and Valerie

April 11 Update from your Construction Oversight Group (COG)
More roofing, more enclosure, more partitions!  Ice & Watershield membrane has been installed over most of the new roof; the other half of the roof is now ready to be framed, with the new North Stair addition and roof to follow. The gray sheets installed over the Tyvek on the playground side are a cementitious board for fireproofing; as our building is so close to the lot line, we are required to provide an extra layer of protection.
At the North Stair, check out the photo of the angling steel – that’s the side of part of the new stairwell, from Sanctuary level up to the Offices level. We’re standing down in the CC level bathrooms and Mechanical room.
We have also been finalizing a lot of the finishes for the floors, ceilings, cabinets. We have a beautiful palette, and will try to bring some of the samples to coffee hour, so you can see the colors and wood and tile.  And, of course, we’ve many, many meetings and emails about HVAC, site grades, door hardware and locks, lighting, AV…so much dedicated work by so many!
Is it really April?!  Alice and Valerie


April 4 Update from your Construction Oversight Group (COG)
We have roof! We have walls! We have Tyvek!  And we promise, there will be window openings, lots of them.
The framers are moving fast and we on COG were able to climb up our new South stairway (on the Waldorf driveway side) to see the actual spaces on the top floor for the first time. The new Sonin Music Room is going to be lovely and spacious – the photos are looking up at the new ridge beam, which roughly defines the shape of the new room (the diagonals in the foreground are temporary bracing). It will be even more real when the roof framing – and the skylight opening – show up, later today.
We are eagerly looking forward to seeing the north stair, next to the elevator shaft, and the connection to the new terrace space between Marshman and Sanctuary. The meeting/class rooms and the offices are taking shape as they raise the partition walls and we were able to measure for the kitchenette cabinets. So good to be above ground!
We continue to tussle with a number of areas;  HVAC ducting coordination, landscape pricing and the constant steam of questions about door hardware, walk-off mats, lighting, audio-visual options etc. etc. As we work to contain the budget and to balance unexpected over-runs with cost-cutting, we very much appreciate the vote by Program Council in support of our use of the pre-approved ‘contingency’ tap on the Heritage Fund, an endowment fund specifically set aside for the building. It means a lot to us to have such support from the congregation and from the leadership.
Also, some very happy news as we look forward to Moving Back In over the summer: Jane Spickett and Jackie Hawkinson are returning to manage the move in! We are delighted and thank them in advance.
Happy April, Alice and Valerie

 


March 28 Update from your Construction Oversight Group (COG)

Major Construction Milestone: We Topped Off the Building!

Follen passed a major milestone in the construction/renovation project yesterday with the topping-off of the building. This means the top piece of structural framing was put in place – the trusses that form the roof were dropped onto the top story walls by a huge crane. And, following long-standing building tradition, we attached a small pine tree to the truss, festooned with ribbons, to be the highest point. We signed the truss before it flew up into the air, and then we toasted everyone who worked on the project. Rev. Claire read an excerpt of a poem to celebrate the moment. What a happy occasion!

Now, after months of complicated, but necessary, foundation work, we can see the outline of the finished space. All that remains is enclosing the structure, drywalling, electrical work, plumbing, cabinetry, flooring, painting … okay, there’s a little bit left to be done, but it should be finished by summer!

Here is the poem Rev. Claire read:

For a New Home by John O’Donohue

May this home be a place of discovery,
May it be a home of courage,
Where healing and growth are loved,
Where dignity and forgiveness prevail;
A home where patience of spirit is prized,
And the sight of the destination is never lost
Though the journey be difficult and slow.
May there be great delight around this hearth.
May it be a house of welcome
For the broken and diminished.
May no guest leaves without a blessing.

Finally, Check out Joe Turner’s pictures of the event, including drone shots of the little evergreen placed on top!

 


March 21 Update from your Construction Oversight Group (COG)

Spring has sprung and the building site is buzzing. Framing has finally started on the top level and walls are going up, and we expect to see a ridge sometime next week. Wow! Roofing will follow very quickly, and we on COG will try for a ‘topping-off’ ceremony in the middle of it all. Watch this space!

And, a big concrete pour yesterday. Thankfully it went quickly, as the concrete truck had to wedge itself on the Marshman front lawn; our Barnes Place neighbors have quite a construction site to live next to, and we’re grateful for their patience!

We on COG continue to work on value-engineering, to reduce costs. We’re developing alternate landscaping approaches, purchasing appliances and some lighting ourselves, and are going to be building some of our own kitchenette cabinets. Those of you who enjoy assembling IKEA cabinets- let us know if you’d like to help!

Hooray for Spring! Alice & Valerie